Creating an effective Project Board
13 October 2011
Written by: David Geoffrey Litten
What are the secrets to an effective Project Board?
Senior Management Project Board
Representation

As with any endeavor, there needs to be appropriate representation of senior
management, the trouble is, most senior managers don't know what is needed from them nor how they need to direct
and authorize a typical project.
This has been addressed at long last in a publication called
"Directing Successful Projects With PRINCE2". It is
also a problem that senior managers are too busy running the company to attend training events, again, you
will find help on that aspect in this article.
Now don't be concerned if your organization does not use PRINCE2 (although I believe
it should!), instead read the following as a solid methology, a bible if you will, to those who either sit on
project boards, or those who sit at programme level (the programme manager for example). I use here, the UK
spelling for program.
CLICK HERE if you want to view my Project Board
Briefing.
-
First you need to understand the roles and responsibilities that are
needed:
PRINCE2 is based on a customer/supplier environment, and this drives the
project’s structure of roles and responsibilities. PRINCE2 does not define jobs allocated to people,
but rather, it defines roles, each with a set of responsibilities. Each role may have one person or
several people filling it, an individual may fulfil more than one role.
What is important is that the right people are chosen for each role, and
this would include the individual’s knowledge, skills, experience, authority, credibility, commitment
and availability.
PRINCE2 has a reserved term for the project board, project manager, and
some optional roles, and this term is called the Project Management Team. A PRINCE2 project always have
three primary categories of stakeholder, and these must always be included if the project is to be
successful.
The three primary interests that make up the project board are the
Business interest – the Business Case should provide value for money, the User interest – these will
use the project’s outputs either to realise the benefits, they may operate, maintain or support the
project outputs, and these outputs will impact them, and the Supplier interest – these supply the
resources and skills to produce a project’s products.
There are four levels within a PRINCE2
organisation:
1. Corporate or programme
management, these are outside of the project management team, and are responsible
for the Project Mandate, naming the Executive, and defining the project-level tolerances.
2. The Project
Board is responsible for providing the overall direction and are accountable for
the success of the project
3. The Project Manager is responsible for the day-to-day management of
the project within the constraints laid down by the Project Board.
4. Team members are responsible for delivering the project products
within quality, time and cost
The Project Board
responsibilities include being accountable for the success or failure of the project, providing
unified direction, providing the resources and authorising the project funding, and ensuring
effective decision-making.
The Project Board should have the right level of authority, be credible,
have the ability to delegate, and be available for whenever that decisions and directions are
needed.
The Project Board
Executive is ultimately accountable for the project success and has the veto on
any decision making. The executive is responsible for the Business Case.
The Senior User
role represents those who will use the project’s products and also those who will use the products to
achieve an objective or deliver benefits. The Senior User specifies the benefits and is held to account
by corporate or programme management.
The Senior
Supplier role represents those who will design, develop, facilitate, procure, and
implement the project’s products. This role is responsible for the technical integrity of the
project.
Each Project Board member is responsible for their own assurance,
business, user and supplier. Collectively, this role is called Project Assurance. Each project board
member can perform their own project assurance, or they may choose to delegate it.
Project assurance
must be independent of the Project Manager and the team and are also responsible for supporting the
project manager by giving advice and guidance.
If the project is likely to have many change requests, then the project
board during the initiation stage, need to decide whether they have the time to make decisions on these
changes, or whether they wish to set up a Change Authority who will act upon their behalf. They would
need to agree to ‘rules of engagement’.
For example, the project board may only deal with changes above a certain
monetary value. The Project Board may also wish to consider allocating a separate change budget to pay
for such changes.
The Project Board should not exceed six to eight people otherwise
decision-making can be slowed, it is a good idea to consider having off-line supplier and user
meetings, and bring a representative back to the project board to act on their behalf..
The project manager is responsible for day-to-day management of the
project and will delegate responsibility for the creation of products to the team manager or specialist
team members themselves.
If the team manager is
appointed, then the project manager will give the Work Packages to the team manager, and the team
manager will give the project manager regular Checkpoint Reports. The Team Manager will therefore
perform the daily management of the team members.
Another optional role is the use of Project Support. This group will
provide administrative services to the project, give advice and guidance on the use of project
management tools, and will normally provide configuration management. It project support is not
available, then the project manager will have to do it themselves.
The project board use the Directing a Project process to provide
direction and authorisation to the project at key points. This enables the project board to be
accountable for the project’s success by ensuring that key decisions are made while exercising overall
control.
The project board delegate day-to-day management of the project to the
project manager, and release the project to the project manager one stage at a time.
Directing the project has six key
objectives, and they ensure that:
1. There is appropriate authority to initiate the project
2. There is authority to deliver the project products
3. The project remains viable and management direction and control are in
place throughout the projects life.
4. The project board executive Interface is regularly with corporate or
programme management
5. There is authority to close the project
6. A benefit review plan for realising the post project benefits is
created, managed and reviewed.
Directing a project contains four activity points where key decisions are
made. Authorising Initiation, Authorizing a Project, Authorizing a Stage or Exception Plan, and
Authorizing project closure.
The fifth activity point is used primarily for communication between the
project board, the project manager and other key stakeholders. This is called Give ad-hoc
direction.
The Directing a Project process starts when the Starting Up a Project
process is completed and is triggered by the request from the project manager to initiate a
project.
The project board uses the technique management by
exception. It monitors via reports and provides control via a number of the
decision points.
For management by exception to work, the project board must set
tolerance,
and if at any point this is forecasted to be exceeded, the project
manager will inform the project board via an Exception Report to bring the situation to the project
board’s attention.
With management by exception there is no need for progress meetings. As
already mentioned there must be an information conduit between the project board and corporate or
programme management (Give ad-hoc direction), how this is to occur should be documented in the
Communication Management Strategy.
Although it is the executive of the project board who has the veto on any
decisions and direction given, the project board should provide a unified direction and guidance to the
project manager and other key stakeholders.
The project board is responsible for assuring that there is continued
business justification, and this is why the project Board Executive owns the project Business
Case.
The five activities within Directing a
Project are:
1. Authorise initiation
2. Authorise the project
3. Authorise a stage or exception plan
4. Give ad hoc direction
5. Authorise project closure
For much more information
on an effective Project Board
CLICK HERE
Source: http://pm-primer.com
David spent 25 years as a senior project manager for US multinationals and now develops a wide range of
project-related downloadable video training products under the Primer brand. In addition, David runs
training seminars across the world, and is a prolific writer on the many topics of project management. He
currently lives in Spain with his wife Jude.
|